Sabine Liquefaction Expansion Project Schedule – Trains 5 & 6

February 27, 2013 – Submitted NEPA Pre-Filing Request

March 8, 2013 – Received FERC Approval to use Pre-Filing Process

September 30, 2013 – Filed NGA Section 3 Application

April 6, 2015 – Issuance of Authorization

April 13, 2015 – Filed Initial Implementation Plan

June 30, 2015 – Commenced Construction on Train 5

Q3 - 2019* – Train 5 In-Service

*dates are estimates and are subject to change