Project Schedules

February 23, 2018 – Submitted NEPA Pre-Filing Request

March 8, 2018 – Received FERC Approval to use Pre-Filing Process (FERC Docket PF18-3-000)

April 17, 2018 – Open House at Johnson Bayou Community Center, from 3 – 7pm.  Click here for map. 

September 7, 2018 – File NGA Section 3 Application

October 2019 – FERC Issuance of Environmental Assessment

January 2020 – FERC Issuance of Authorization

 