Top 5 Global Supplier of LNG by 2020

Sabine Pass Terminal Corpus Christi Project

FERC Process

 

Federal Energy Regulatory Commission Process

On December 13, 2011, Corpus Christi Liquefaction requested FERC's permission to engage in the Pre-Filing Environmental Review Process (Reference Docket No. PF12-3-000). The pre-filing process provides opportunities for federal and state cooperating agencies (TCEQ, USACE, USFWS, etc.), and other public stakeholders to comment on the project impacts prior to an application to the FERC being submitted. Permission was granted to begin the pre-filing process on December 22, 2011.

 