Project Schedule


Sabine Liquefaction Expansion Project Schedule – Trains 5 & 6

February 27, 2013 – Submitted NEPA Pre-Filing Request

March 8, 2013 – Received FERC Approval to use Pre-Filing Process

September 30, 2013 – Filed NGA Section 3 Application

April 6, 2015 – Issuance of Authorization

April 13, 2015 – Filed Initial Implementation Plan

June 30, 2015 – Commenced Construction on Train 5

Q3 - 2019* – Train 5 In-Service

*dates are estimates and are subject to change

Last updated 06/13/16
Sabine Pass Liquefaction Construction Commissioning in 2016 LNG Terminals
Annual Report Cheniere Energy’s 2016 Annual Report Recent Annual Reports
Careers Build a future with Cheniere Energy Careers
Community Relations Cheniere is proud of the role we play in the communities where we operate and live Community Relations
Safety and Environment Our constant goal 100% safe and incident free facilities Safety and Environment
Cheniere Offices Professional staff based in London, Houston, Santiago and Singapore Map
Craft Development Program Over 150 accepted and over 30 graduates employed Careers in Craft Development Program
®2017 Cheniere Energy, Inc. Copyrights - All Rights Reserved