Home Contact Us

  LNG Terminals
  Terminal Management
  Operations & Maintenance
  Frequently Asked Questions
  LNG Contractors


  Sabine Pass Terminal
   - Liquefaction Project
   - FERC Process
   - Project Schedule
   - Documentation
   - Public Open House
   - Contact Information

   - Liquefaction Expansion
   - Documentation
   - Project Schedule


  Corpus Christi Project
   - FERC Process
   - Project Schedule
   - Documentation
   - Contact Information

  Investor & Media
  Safety & Environment
  Community Relations

  Career Opportunities

Sabine Liquefaction Project Schedule
July 26, 2010 Submitted NEPA Pre-Filing Request
August 4, 2010 FERC Approval to use Pre-Filing Process
January 31, 2011 File NGA Section 3 Application
December 28, 2011 Issuance of Environmental Assessment / Environmental Impact Statement
January 31, 2012 File Initial Implementation Plan
April 16, 2012 Issuance of Authorization
3rd Q - 2012 Commence Construction
4Q 2015* Liquefaction Project In-Service

 

*dates are estimates and are subject to change