Home Site Map Contact Us

  LNG Terminals
  Terminal Management
  Operations & Maintenance
  LNG Contractors


  Sabine Pass Terminal
   - Liquefaction Project
   - FERC Process
   - DOE Applications
   - Project Schedule
   - Documentation
   - Public Open House
   - Contact Information
   - FAQ's


  Corpus Christi Project
   - FERC Process
   - Project Schedule
   - Documentation
   - Contact Information
   - FAQ's

  Investor & Media
  Safety & Environment
  Community Relations

  Career Opportunities

Corpus Christi Liquefaction Project Schedule
December 13, 2011 Submitted request to initiate pre-filing review process
December 22, 2011 Issuance of FERC approval to begin pre-filing process
August 31, 2012 File FERC Application
May 2013* Issuance of Environmental Assessment / Environmental Impact Statement
September 2013* Issuance of FERC order
August 2013* File Initial Implementation Plan
By Mid-2014* Commence Construction
December 2017* Liquefaction Project In-Service

*dates are estimates and are subject to change